Skip to content
Pass Any WGU OA Exam Now & Pay After You Pass. Contact Us!
  1. Home
  2. WGU Exams
  3. WGU C722
  4. Set 4
WGU C722 · Project Management

WGU C722 Practice Questions – Set 4

50 multiple-choice questions with answers and detailed explanations. Untimed — choose an answer to check it instantly.

Question 1 of 50

In project management, what document describes the project's objectives, key deliverables, and a rough cost estimate to formally authorize the project?

Question 2 of 50

What term is used to describe the difference between the baseline schedule and the actual schedule, indicating whether a project is ahead or behind?

Question 3 of 50

Which project management method emphasizes managing uncertainties by building time buffers into the schedule?

Question 4 of 50

What is the main purpose of the Requirements Management Plan?

Question 5 of 50

What type of project organizational structure combines features of both Functional and Projectized structures?

Question 6 of 50

What process involves using prior project data and historical knowledge to estimate costs for a current project?

Question 7 of 50

What project scheduling tool visually displays tasks and their durations over time, often with bars representing each task?

Question 8 of 50

What document helps track and monitor the progress of customer requirements to ensure they are met throughout the project?

Question 9 of 50

In risk management, what technique shifts risk from the project team to a third party, such as through insurance?

Question 10 of 50

Which Agile methodology term describes the prioritized list of features that the team works from during a Sprint?

Question 11 of 50

Which scheduling technique calculates the shortest project duration by focusing on the path with the longest sequence of dependent tasks?

Question 12 of 50

What is the purpose of resource leveling in project scheduling?

Question 13 of 50

Which rule in Earned Value Management allows 50% of a task’s value to be assigned when it starts, with the remaining 50% upon completion?

Question 14 of 50

What term describes costs that support multiple project activities but cannot be tied directly to one specific task?

Question 15 of 50

In a Matrix organizational structure, what is a common challenge project managers face?

Question 16 of 50

What type of cost is incurred as the project progresses and varies with the level of output, such as materials and labor?

Question 17 of 50

What does the Schedule Performance Index (SPI) measure in project management?

Question 18 of 50

Which document formally approves the initiation of a project and assigns resources to begin work?

Question 19 of 50

Which estimation technique applies a three-point approach, averaging optimistic, most likely, and pessimistic values?

Question 20 of 50

In which project phase are deliverables handed over to the customer, and final documentation is completed?

Question 21 of 50

What term describes tasks that must be completed in a specific order, without the option for overlap?

Question 22 of 50

In which project management phase is the project schedule and budget finalized with sponsor approval?

Question 23 of 50

What does “float” or “slack time” refer to in project scheduling?

Question 24 of 50

Which project management term is used to refer to a potential benefit or improvement that a risk could bring to a project?

Question 25 of 50

What document identifies the key project stakeholders, their interests, and communication needs?

Question 26 of 50

What approach is used to develop the cost baseline by calculating the cumulative project costs over time?

Question 27 of 50

What is the purpose of a Quality Audit in project management?

Question 28 of 50

What Agile practice involves holding a daily meeting where team members share updates on their progress and plans?

Question 29 of 50

What method evaluates a project by calculating the time needed to recover the cost of the project?

Question 30 of 50

Which term describes the act of setting project requirements, scope, and baselines, with a focus on project objectives and deliverables?

Question 31 of 50

Which Agile term describes the process of reviewing and updating the Backlog to ensure priority tasks are clear and prepared for upcoming Sprints?

Question 32 of 50

What project management term describes the total time that a task can be delayed without impacting the project's end date?

Question 33 of 50

Which document details the specific technical and business requirements necessary for a project's success, guiding scope and design?

Question 34 of 50

What estimation method uses a ratio or unit rate, such as cost per square foot, to estimate overall project costs?

Question 35 of 50

What project term describes the longest chain of dependent activities that determines the shortest possible project duration?

Question 36 of 50

In project management, what is the primary function of a Resource Histogram?

Question 37 of 50

Which phase involves capturing lessons learned and confirming that all deliverables have been completed and accepted?

Question 38 of 50

In project management, what term refers to the set of documents that outline the approved scope, cost, and schedule baselines?

Question 39 of 50

What is the purpose of a Risk Breakdown Structure (RBS)?

Question 40 of 50

What task dependency requires a task to be delayed until a specified predecessor task is completed?

Question 41 of 50

Which type of estimating provides a range for task durations, accounting for uncertainties by using best, worst, and most likely scenarios?

Question 42 of 50

What type of project cost includes expenses like office utilities and administrative salaries, which are shared across multiple activities?

Question 43 of 50

What does Earned Value (EV) represent in project management?

Question 44 of 50

In Agile, what is the purpose of a Sprint Retrospective?

Question 45 of 50

What does the Project Scope Statement primarily describe?

Question 46 of 50

What type of project management approach organizes tasks into linear, sequential phases, often used in software development?

Question 47 of 50

In project budgeting, what are Direct Costs?

Question 48 of 50

Which project selection technique focuses on projects aligned with strategic objectives and operational priorities, even without clear financial returns?

Question 49 of 50

What is the purpose of a Work Breakdown Structure (WBS) in project management?

Question 50 of 50

In project cost management, what is the primary purpose of Earned Value Management (EVM)?

Set 4 complete

You scored 0%

0 correct out of 0 answered (50 questions in this set).

Next: Set 5

Struggling with WGU C722?

If this exam is giving you a hard time, let us be your helping hand. Contact us, and we'll provide the assistance you need to pass and move forward.

Chat Now