Skip to content
Pass Any WGU OA Exam Now & Pay After You Pass. Contact Us!
  1. Home
  2. WGU Exams
  3. WGU C722
  4. Set 2
WGU C722 · Project Management

WGU C722 Practice Questions – Set 2

50 multiple-choice questions with answers and detailed explanations. Untimed — choose an answer to check it instantly.

Question 1 of 50

What is the most common relationship between tasks in a project schedule, where the successor activity cannot begin until the predecessor activity has been completed?

Question 2 of 50

In project cost management, what is the difference between the Earned Value (EV) and the Actual Cost (AC) used to determine?

Question 3 of 50

Which phase includes identifying and defining project requirements, as well as documenting scope, stakeholders, and high-level risks?

Question 4 of 50

What type of organizational structure is characterized by having clear lines of authority within departments and is commonly used in government agencies?

Question 5 of 50

Which project management method organizes tasks into a linear sequence where each phase must be completed before moving to the next?

Question 6 of 50

What cost estimation method leverages prior project data to calculate costs based on unit costs or rates?

Question 7 of 50

In Agile project management, what document is created to capture all required features and functionality as requested by the customer?

Question 8 of 50

What technique is used when compressing a schedule by assigning additional resources to critical tasks?

Question 9 of 50

Which term refers to adjusting tasks or activities to reduce peaks and valleys in resource allocation, helping maintain consistent resource use?

Question 10 of 50

In a project, what kind of costs are directly related to completing the work and can be clearly attributed to specific tasks?

Question 11 of 50

Which type of cost estimation starts with the highest level and progressively refines costs as more information is available?

Question 12 of 50

Which project phase involves reassessing project objectives and reassigning resources for future use once deliverables are accepted?

Question 13 of 50

What tool provides a visual representation of resource requirements over time and is helpful for balancing resource allocation?

Question 14 of 50

What is an “Opportunity” in risk management terms?

Question 15 of 50

Which type of task dependency requires a task to be delayed before its successor can begin?

Question 16 of 50

What estimating technique calculates an average by weighting the most likely estimate more heavily than optimistic and pessimistic estimates?

Question 17 of 50

Which document establishes how stakeholders will be identified, their level of interest, and communication needs throughout the project lifecycle?

Question 18 of 50

What analysis evaluates whether the project’s budget expectations align with actual spending, using Earned Value (EV) and Actual Cost (AC) data?

Question 19 of 50

Which estimating technique would be appropriate when activity durations are highly predictable?

Question 20 of 50

What is the term for the calculated difference between the finish date of the last activity on the critical path and the project’s scheduled completion date?

Question 21 of 50

In which project management phase are deliverables formally handed over to the customer?

Question 22 of 50

Which rule in Earned Value Analysis assigns 50% completion when a task begins and the remaining 50% upon task completion?

Question 23 of 50

What is the amount added to the overall project budget to account for unforeseen costs known as?

Question 24 of 50

What phase concludes with the approval of the project charter?

Question 25 of 50

What is a PERT chart primarily used for in project management?

Question 26 of 50

Which term is used to describe an iterative, time-boxed work period in Agile project management?

Question 27 of 50

What is the purpose of a Network Diagram in project management?

Question 28 of 50

Which document serves as a central record of identified risks, their assessments, and responses?

Question 29 of 50

Which project phase requires the most resource allocation as tasks are actively being completed?

Question 30 of 50

What term refers to delaying tasks intentionally to balance the workload among project resources?

Question 31 of 50

Which risk response strategy involves eliminating the cause of a risk so that it no longer has any impact on the project?

Question 32 of 50

What kind of cost is included in the budget to address potential project risks and is part of the baseline budget?

Question 33 of 50

Which rule in Earned Value Analysis (EVA) assigns 100% completion to an activity only when it is fully completed, with no partial credit given?

Question 34 of 50

Which project document defines the criteria by which the project will be deemed complete and successful?

Question 35 of 50

What term describes additional time that can be added to project activities without delaying the overall project?

Question 36 of 50

Which scheduling method is used to calculate the earliest and latest start and finish times for each project activity?

Question 37 of 50

What technique would be used to calculate the average task duration based on optimistic, most likely, and pessimistic estimates?

Question 38 of 50

Which type of organizational structure provides the project manager with the least amount of authority?

Question 39 of 50

Which type of reserve is used to cover unknown or unexpected risks that might arise during a project?

Question 40 of 50

What type of costs are considered indirect costs and cannot be assigned to any single activity within the project?

Question 41 of 50

What does a Cost Performance Index (CPI) greater than 1.0 indicate about a project's financial performance?

Question 42 of 50

Which type of estimate uses historical data and applies statistical relationships to forecast project costs?

Question 43 of 50

Which project selection model emphasizes factors beyond traditional financial metrics, such as strategic alignment and competitive positioning?

Question 44 of 50

Which Agile practice involves a team reflection on what went well and what could improve after each work cycle?

Question 45 of 50

In Agile, what is the prioritized list of project requirements that guides team tasks?

Question 46 of 50

What describes an organization’s strategy for selecting projects that support its long-term goals and mission?

Question 47 of 50

Which project phase involves assessing lessons learned and archiving project information for future reference?

Question 48 of 50

Which estimation technique provides a single value for task duration based on expert judgment or past data?

Question 49 of 50

What phase ends once project baselines for scope, schedule, and budget are approved?

Question 50 of 50

In project management, what is the term for assigning additional resources to shorten the project schedule?

Set 2 complete

You scored 0%

0 correct out of 0 answered (50 questions in this set).

Next: Set 3

Struggling with WGU C722?

If this exam is giving you a hard time, let us be your helping hand. Contact us, and we'll provide the assistance you need to pass and move forward.

Chat Now