Skip to content
Pass Any WGU OA Exam Now & Pay After You Pass. Contact Us!
  1. Home
  2. WGU Exams
  3. WGU C722
  4. Set 3
WGU C722 · Project Management

WGU C722 Practice Questions – Set 3

50 multiple-choice questions with answers and detailed explanations. Untimed — choose an answer to check it instantly.

Question 1 of 50

What does the Project Scope Statement include to define the boundaries of a project?

Question 2 of 50

In project management, what is the primary purpose of a “Change Control Board (CCB)”?

Question 3 of 50

Which cost estimation technique begins by identifying the smallest level of tasks and aggregating their costs?

Question 4 of 50

Which type of reserve is used for planned and anticipated project risks?

Question 5 of 50

In project scheduling, what term describes the delay added to an activity to align with its successor task?

Question 6 of 50

What Agile project management term is used for prioritizing project work and functionality over time-bound delivery?

Question 7 of 50

What is a “Risk Appetite” in the context of risk management?

Question 8 of 50

Which project phase formally recognizes the start of the project and includes the creation of a project charter?

Question 9 of 50

What tool is a visual representation used in project management to sequence activities based on their dependencies?

Question 10 of 50

In which project phase is the Work Breakdown Structure (WBS) first developed?

Question 11 of 50

What process occurs when additional features or requirements are added to a project without approval, often impacting scope?

Question 12 of 50

What estimation method uses previous projects of similar scope as a reference to estimate a current project’s costs?

Question 13 of 50

Which project scheduling tool displays task durations and start and end dates in a bar chart format?

Question 14 of 50

What is the primary purpose of a project’s “Scope Baseline”?

Question 15 of 50

Which of the following is NOT a type of Agile methodology?

Question 16 of 50

What term describes activities that can be performed simultaneously if resources allow?

Question 17 of 50

In Earned Value Management, what does the term Planned Value (PV) represent?

Question 18 of 50

Which risk response strategy focuses on reducing the impact of a risk if it occurs?

Question 19 of 50

Which project selection method assigns scores based on selected criteria to rank potential projects?

Question 20 of 50

Which Project Management Institute (PMI) document provides globally recognized project management standards and guidelines?

Question 21 of 50

What type of costs are considered direct overhead costs, supporting multiple activities but not directly attributable to one specific task?

Question 22 of 50

What process ensures that only approved changes are implemented in the project, maintaining control over scope?

Question 23 of 50

What Agile methodology term describes the customer-prioritized requirements that guide development work?

Question 24 of 50

Which project phase focuses on finalizing and delivering all project deliverables to the client?

Question 25 of 50

Which task dependency type means a successor task cannot start until its predecessor has started?

Question 26 of 50

Which process identifies who will be involved in a project and outlines their roles and responsibilities?

Question 27 of 50

What does a “Phase Gate” refer to in project management?

Question 28 of 50

Which document identifies and organizes all project tasks, assigning unique codes to activities and deliverables?

Question 29 of 50

What technique reduces schedule duration by overlapping activities that are usually sequential?

Question 30 of 50

Which estimation technique assigns a single value for task duration based on expert opinion or historical data, without calculating a range?

Question 31 of 50

What is the purpose of the “Resource Responsibility Matrix” in project management?

Question 32 of 50

What is the primary purpose of the Requirements Traceability Matrix?

Question 33 of 50

Which scheduling technique adds intentional overlap to sequential tasks to reduce project duration?

Question 34 of 50

In which phase does the project manager confirm that all project requirements have been met and accepted by the client?

Question 35 of 50

Which term refers to the additional time given to a task that will not delay the project’s overall completion date?

Question 36 of 50

What is the main function of a Gantt Chart in project management?

Question 37 of 50

Which project management term defines the minimum resources necessary to complete a project?

Question 38 of 50

What term is used for the total approved budget for a project, including all costs and reserves?

Question 39 of 50

Which project management term represents the risk acceptance level where a stakeholder shows interest in risk exposure?

Question 40 of 50

What is a “Phase Gate” used for in project management?

Question 41 of 50

Which task dependency type means the successor task cannot finish until the predecessor task is completed?

Question 42 of 50

What estimation technique is best suited for situations where a single, experienced person provides an estimate based on expertise?

Question 43 of 50

In which project phase are resources typically reallocated to other projects after completing their assignments?

Question 44 of 50

What is the purpose of a Stakeholder Analysis?

Question 45 of 50

Which project management approach uses iterative cycles for development and emphasizes customer feedback?

Question 46 of 50

What project document outlines the strategic benefits, costs, and reasons for initiating the project?

Question 47 of 50

What type of project cost includes day-to-day expenses, such as utilities, that cannot be directly attributed to the project’s deliverables?

Question 48 of 50

What is the term for the process of evaluating and validating that project deliverables meet the required standards and specifications?

Question 49 of 50

Which document captures all potential risks, risk scores, response plans, and the individuals responsible for managing them?

Question 50 of 50

What is a Stakeholder Management Plan primarily used for in a project?

Set 3 complete

You scored 0%

0 correct out of 0 answered (50 questions in this set).

Next: Set 4

Struggling with WGU C722?

If this exam is giving you a hard time, let us be your helping hand. Contact us, and we'll provide the assistance you need to pass and move forward.

Chat Now